L.A.C.T. UNIT DESIGN |
|
By Welker
Flow Measurement Systems, Inc. 13839
West Bellfort Sugar
Land, Texas 77478
|
The Lease Automatic Custody
Transfer (L.A.C.T.) unit is designed for the automatic transfer of ownership of
crude or condensate between the buyer and seller.
This can be on land or
offshore, into pipelines, barges, and tanker loading and offloading operations.
On land L.A.C.T. units are
usually small, single run systems with portable proving connections designed for
loading into trucks.
Because of the geographical
area, this paper will focus on the offshore L.A.C.T. units. These are dual run
with 100% back-up and with mechanical displacement meter provers at 150 ANSI
working pressures.
The basic components and
function of a L.A.C.T. unit are:
1. Charge Pump and Motor - Largely overlooked and undersized, special care should be taken into consideration during sizing to ensure correct NPSH is available to prevent cavitation, and discharge pressure is enough to overcome pressure drop through the L.A.C.T. to allow the required flow and pressure to the pipeline pump inlet.
2.
Strainer/Air Eliminator - Strains solids larger than the
perforations in the removable basket with liner. They
should have differential pressure indicator to show pressure drop caused by
debris accumulation and be cleaned periodically. Essential to prevent premature
meter wear or breakage. The air eliminator is located on top of the strainer at
the highest part of the system to allow air to be discharged and not metered.
This should be piped with a soft-seated check valve to prevent air from being
introduced into the system during shutdown.
3.
Sample System - Installed with an upstream static mixer usually
flow-proportional, isokinetic, and tubed to a vapor tight storage vessel sized
to allow 25 to 30 days storage. The vessel is provided with a recirculation
pump, the samples are mixed and then drawn off to be checked for composite API
Gravity and BS&W during the delivery period.
4.
BS&W Monitor and Probe - Installed downstream of the sampler
and upstream of the three-way divert valve, this unit consists of a flanged
probe that monitors the flowing stream for basic sediment and water and
communicates with the "monitor" unit that is normally installed in the
control panel. The "monitor" is usually set at 1.0%, and is wired to
the solenoid valves controlling the three-way valves on the bad oil divert line.
These will send oil to be treated if a high
BS&W
signal is received for a given time. When a good oil signal is received for a
set time, then the valves will return to normal flow position.
5.
Meter - Installed downstream of the three-way valve and downstream
of a properly sized thermal relief valve. The meter measures the product stream
and allows totalization either through a local totalizer or electronic pulses to
a flow computer. This meter can be a positive displacement or turbine meter.
The
meter will provide signals to the flow computer or PLC to allow:
Sample Pacing
Totalization
Meter Proving
Meter Fail
6.
Meter Instrumentation - Downstream of the meter a spool consisting
of:
Temperature transmitter with platinum RTD installed in a S.S. thermowell.
Pressure transmitter with a pressure gauge mounted with a three-way gauge valve.
Test S.S. thermowell used to calibrate the temperature transmitter.
The temperature and pressure transmitters are used to
send a live reading to the flow computer for compensation.
7.
Check Valves - Downstream of the meter to prevent backflow to the
meter in case the downstream block and bleed valve is left open and the opposite
meter train is running.
8.
Block and Bleed Valves - Located downstream of the check valves at
the end of each run and as the main line divert valve separating the to and from
lines to the prover four-way divert valve. This is to ensure all fluid is being
diverted to the prover during proving, or a false meter factor could be obtained
during proving of the meter.
9.
Prover Instrumentation - On the outlet of the prover four-way divert
valve a spool consisting of:
Temperature transmitter with platinum RTD installed in a
S.S. thermowell.
Pressure transmitter with a pressure gauge mounted with a
three-way gauge valve.
Test S.S. thermowell used to calibrate the temperature
transmitter.
Thermal relief valve properly sized.
10.
Back Pressure Valve - On the skid outlet to maintain pressure
above the vapor pressure of the fluid being metered and provide a constant
pressure and flow on the meter during proving.
11.
L.A.C.T. Control Panel - This can be located on the skid with PLC
controls and local manual proving connections would then be required, for a
prover counter, detector switch plug in, power for the counter, and a portable
pulse generator for P.D. meters.
An
electronic temperature averager could then be used in lieu of temperature
transmitters; however, due to their flexibility and relative cost, flow
computers are rapidly replacing them.
If
located in the MCC room, the panel could then be equipped with a PLC, flow
computer, and printer to allow for automatic proving and batch reports by
pushing a button, provided the prover's four-way valve is equipped with a remote
actuator, and pressure and temperature transmitters were installed.
The
control panel will have the following functions:
Start and Stop Off High and Low Level Switches
Hand-Off-Automatic Switch
BS&W Divert Controls
Meter Fail
Monitor Failure
Internal Battery Back-Up for Power Loss
12.
Calibrated Bi-Directional Meter Prover - Because of the versatility of
configuring a bi-directional prover in tight offshore spaces and its' cost
associated with normal offshore flow rates; the bi-directional prover has become
the prover of choice versus the uni-directional and small volume prover.
The
continuous flow technique of meter proving is accomplished by repeatable
displacement of a known volume of liquid in a calibrated section of pipe between
two signaling devices (detector switches).
A
slightly oversize prover sphere inflated to normally 2% over the pipe inside
diameter is used to displace the fluid.
The
fluid is run through the meter and the prover. The metered volume is recorded by
the electronic meter proving counter (built into flow computers).
The
known volume displaced is checked against the meter's indicated output and a
"meter factor" is obtained after correction factors (Ctl)(Cps)(Cts)
and (Cpl) are applied.
The
use of new work over chemicals now seen offshore suggests internal coatings be
exclusively a baked on phenolic versus an air-dried epoxy for longer life.
The prover sphere most seen nowadays has gone from the standard 53 Durometer hardness to a 58 Durometer harder material for longer life and durability.
Design Considerations
*Customer's Specifications
First and foremost, if your
L.A.C.T. unit does not meet your buyer's or shipper's standard specifications,
you may find yourself offshore with a tank full of oil having to shut in your
wells because your L.A.C.T. skid has not been approved, or they just were
notified that you want to come on-line with a skid they have never seen. Get
hold of the specifications and get them involved early in the fabrication of the
unit.
*Space
Offshore space is a premium.
Units can be built in any number of configurations and footprints, but also
consider the serviceability of the unit. Viscosity
High viscosity can cause
several problems.
1.
Does the meter (P.D. type) require high viscosity clearances and
temperature trim on units above 150° F?
2.
If heat traced and insulated, the instrumentation may require new trim.
3.
Check prover sphere operating temperature.
4.
Is NACE trim required?
Flow Rates
Is the L.A.C.T. unit only
going to see one platform's oil, or is there a chance that a new platform's oil
will be shipped over next year when it comes on-line?
Do you need to design the
skid for an additional meter run?
Conclusion
The recent acceptance and
development of new electronic equipment for crude oil measurement in the past
few years has made them more reliable and accurate while requiring less
maintenance. However, the technician needs to be more highly trained than ever
before.
Many factors go into the
design of L.A.C.T. units flow rates, space limitations, temperature, viscosity,
corrosion, and customer specifications. As long as these are taken into
consideration, one can end up with a quality measurement system.